十七层框架剪力墙新城6栋工程施工组织设计★
十七层框架剪力墙新城6栋工程施工组织设计★(含选题审批表,任务书,开题报告,中期检查报告,施工组织设计书30000字,cad图纸43张)
摘 要:施工组织设计是建筑施工组织的核心和灵魂,是施工的技术、经济和组织的综合性文件,用来指导工程项目施工的各项活动。本施工组织设计是澧县大汉新城6#栋工程施工的纲领性文件,主要内容包括项目管理机构设置、施工总体部署、施工准备、主要分部分项工程施工方法、工程质量保证措施、安全及文明施工措施、施工现场管理措施等。本施工组织设计根据现场实际情况提出了具体的施工方案和进度计划保证措施,以达到工期短、质量好,成本低的目标。
关键词:施工部署;施工方案;施工进度计划;
The Construction Management Planning for 6th of Dahan
Abstract: The construction management planning is the core and the soul of construction management and also the comprehensive file of technique, economy and management is aim to guide each construction project activity.The construction management planning is the programmatic document for 6th of Dahan New City building in Lixian, including project management organization, the overall arrangement of constrction, construction preparation, the main sub-segment of the construction methods, the quality assurance measures, safety and civilized construction measures and the organizational measure of construction site. The construction management planning comes up with the concrete construction plans and schedule guarantee measures which is based on the construction management planning so as to achieve the goal of short construction period, good quality and low cost target. [版权所有:http://DOC163.com]
Key words: Construction deployment ; Construction scheme ; Construction progress;
2.2.1 建设概况
本工程共17层,结构形式为框架剪力墙形式,建筑类别为二类,耐火等级二级。建筑高度为54.4米,占地面积是529.1平方米,总的建筑面积是8887.8平方米。所有公共走道、楼梯等的墙体均符合防火规范要求的耐火极限,各构件的燃烧性能和耐火极限按《建筑设计防火规范》要求设计。本工程采用了节能设计方法,外墙体、分户墙为240厚加气混凝土砌块。所有填充墙与梁,柱相接处的内墙,及不同砌块之间粉刷应铺设钢丝网,孔眼9×7.5mm,每边铺设宽度不小于250 mm。
2.2.2 结构概况
本工程为框架剪力墙结构,采用长螺旋钻孔灌注桩。建筑抗震设防分类:丙类建筑,抗震设防烈度为7度,抗震等级剪力墙为三级、框架二级。本工程结构设计使用年限为 50年,耐火等级为一级,建筑结构安全等级为二级,抗渗等级为P6。本工程砼强度随楼层不同而变化,具体情况详见表2。
附录
附录1:附图1 施工进度计划横道图
附录2:附图2 施工进度计划网络图
附录3:附图3 施工现场平面布置图
附录4:附图4 建筑设计总说明 [资料来源:http://www.doc163.com]
附录5:附图5 结构设计总说明
附录6:附图6 首层建筑平面图
附录7:附图7 首层结构平面图