珠江广场写字楼工程施工组织设计(工程管理)(附cad图纸)
珠江广场写字楼工程施工组织设计(工程管理)(附cad图纸)(含选题审批表,任务书,开题报告,中期检查报告,毕业论文26000字)
摘 要:本施工组织设计依照建筑工程施工组织设计有关编制原则并结合本工程自身特点进行编制,内容涵盖了工程概况、施工部署、主要分项工程施工方法等多方面的内容。详细分析了施工过程中在安全管理、质量管理、工期保证、季节性施工、现场文明施工等方面可能存在的问题,并提出了相应的保证措施。本设计在整个工程的施工过程中具有重要的指导性作用。能有效保证施工的顺利进行。
关键词:施工组织设计;管理体制;改革;管理;
The Construction Organization Design of ZhuJiang Square Office Project
Abstract: According to the principles of the construction organization design of construction engineering, this construction organization design is constituted combined with the characteristics of this engineering. It includes engineering overview, construction deployment, and the main sub-project construction methods and so on. Some issues which exist in safety management, quality management, guarantee period, seasonal construction, and civilized construction in the process of construction are analyzed in details. And appropriate measures to ensure are put forward. This construction organization design plays an important role in guiding in the process of construction, which can ensure the smooth progress of construction. [资料来源:http://www.doc163.com]
Key words: Construction Design; Management System; Reform; Management
主要内容:工程概况,施工部署,施工准备,主要分项工程施工方法,施工进度计划,安全防护措施,工期与质量管理保证措施,文明施工措施,季节性施工,成本管理及降低成本措施。力求科学、规范、可行。计划编制需要应用网络图同时需要横道图,对资源安置上需要有初步分析和评价。
建筑概况
建设地点:深圳市龙岗区;建筑等级:工程等级为一类超高层,防火等级二级,;总建筑面积:30956.66m2(包括地下室面积3000m2),±0.000 相当于绝对标高76.000m。
1.2 结构概况
工程地质及地表情况本工程底板持力层为硬塑黏土,场地类别:二类(中软场地土);建设单位已经提供“三通一平”的施工场地。
1.2.1 基础形式
本工程采用人工挖孔桩,直径800CM。
本工程为框剪结构、18 层,框架梁、柱、剪力墙及框架均为六级抗震。底层3.9m, 架空层2.7m ,标准层为3m,建筑物总高度67.85m。